1. The choice of installation location is very important. The installation site of the concrete mixer needs to be flat, and the mouth of the pit should be slightly higher than the ground to prevent water from flowing into the pit.
2. Lift the mixer with lifting equipment, install four outriggers, connect angle steel, diagonal braces, ladders, and install upper and lower tracks to align it and place it in the pit. When installing, attention should be paid to keeping the frame on a horizontal plane, and the track frame must not be twisted or misaligned.
3. It is necessary to distinguish the installation operations of different types of concrete mixers. Stationary mixers should be installed on a sturdy base. If it is used for a long time, anchor bolts should be buried. If it is used for a short period of time, wooden sleepers should be laid under the machine and leveled and stabilized.
4. Machinery installation should consider supporting items such as power supply, water source, rainproof measures for material locations and transportation channels.